SPCC plan template: what goes in a self-certified plan
Short answer
A self-certified SPCC plan needs a certification page, a facility description and diagram, a container inventory, secondary containment and drainage controls, transfer and overfill procedures, inspection and testing procedures with records, training, security, and spill response with a contact list. Tier I facilities can use EPA's free Appendix G template; Tier II facilities need a full plan meeting 40 CFR 112.7 and 112.8.
An SPCC (Spill Prevention, Control, and Countermeasure) plan is the written plan 40 CFR Part 112 requires of facilities that store more than 1,320 gallons of oil aboveground where a spill could reach water. If you're a qualified facility, you can write and certify it yourself. Here's every section a self-certified plan needs, and where each requirement comes from.
Two ways to do it yourself
- EPA's Tier I template (Appendix G to Part 112). Free, a fill-in form, and only for Tier I qualified facilities: no aboveground container over 5,000 gallons (§ 112.6(a)). EPA's template page.
- A plan that meets § 112.6(b). Required for Tier II, allowed for Tier I (§ 112.6(a)(1)). It must address § 112.7 and the subpart B or C requirements, and because it won't follow § 112.7's order, it needs a cross-reference table (§ 112.7, introductory text).
Some states publish their own Tier II templates. EPA notes some states don't allow self-certification at all, so check yours first.
Sections a self-certified SPCC plan needs
| Section | What it covers | Rule |
|---|---|---|
| Certification page | The owner or operator's eight statements, signature and date | § 112.6(b)(1) |
| Management approval | Approval at a level that can commit the resources | § 112.7 |
| Qualified facility determination | Aggregate capacity, largest container, 3-year discharge history | § 112.3(g) |
| Facility description and diagram | Layout, each fixed container and its contents, transfer stations, piping | § 112.7(a)(3) |
| Oil inventory | Type of oil and capacity of each container; estimate for mobile/portable ones | § 112.7(a)(3)(i) |
| Discharge prevention and drainage | Routine handling, transfers, drainage controls | § 112.7(a)(3)(ii)–(iii), § 112.8(b) |
| Failure analysis | Direction, rate of flow and total quantity of oil from each likely failure | § 112.7(b) |
| Secondary containment | General containment, plus sized containment for bulk storage: largest container plus rain freeboard | § 112.7(c), § 112.8(c)(2), (c)(11) |
| Bulk storage controls | Compatible containers, overfill prevention, leak correction, buried/partly buried tanks | § 112.8(c) |
| Transfers and piping | Loading racks, buried piping, valves and supports | § 112.7(h), § 112.8(d) |
| Inspections and records | Written procedures, signed records kept 3 years, integrity testing per industry standard | § 112.7(e), § 112.8(c)(6) |
| Training | Oil-handling staff trained; accountable person named; annual briefings | § 112.7(f) |
| Security | How you secure and control access to oil handling, processing and storage areas, master flow and drain valves, pump starter controls, out-of-service piping, lighting | § 112.7(g) |
| Response and reporting | Countermeasures, disposal, contact list, what to report | § 112.7(a)(3)(iv)–(vi), (a)(4)–(5) |
| Review and amendments | Five-year review log; amendments within six months of a change | § 112.5 |
| Cross-reference table | Where each requirement is addressed | § 112.7 |
Where blank templates fall short
- The math is on you. What counts toward the 1,320- and 10,000-gallon thresholds (55-gallon containers and up; not motive power or permanently closed containers) and whether each dike holds the largest container plus rain.
- The failure analysis is site-specific. Direction of flow, rate and quantity for each container (§ 112.7(b)).
- Self-certifiers can't use the escape hatches. No impracticability determinations (§ 112.7(d)) or environmental-equivalence alternatives (§ 112.7(a)(2)) without a PE (§ 112.6(b)(3)). If containment is short, you fix it before you sign.
After you sign
Keep the plan at the facility if it's attended at least four hours a day (§ 112.3(e)); you don't file it with EPA. If oil reaches water, call the National Response Center at 1-800-424-8802 (40 CFR 110.6).
Find out where you stand, free
SpillPlan's free check tells you whether the SPCC rule applies, whether you can self-certify, how big your containment needs to be and what to inspect. If you need a Professional Engineer, it says so. The full plan kit is $549 if you want it.
Next questions
- How to self-certify an SPCC plan
- Tier I vs Tier II qualified facilities under the SPCC rule
- How much does an SPCC plan cost?
- What inspections does an SPCC plan require?
Sources
- 40 CFR 112.6 — Qualified facility Plan requirements and self-certification
- 40 CFR 112.7 — General requirements for SPCC Plans
- 40 CFR 112.8 — Onshore facilities (excluding production): drainage, bulk storage, transfers
- 40 CFR Part 112, Appendix G — Tier I Qualified Facility SPCC Plan template
- EPA — Tier I qualified facility SPCC Plan template
- EPA — SPCC Guidance for Regional Inspectors (2013)
- 40 CFR 110.6 — Notice to the National Response Center (800-424-8802)