Do I need an SPCC plan?
Short answer
You need an SPCC plan if your facility is non-transportation-related, stores or uses oil, could reasonably be expected to spill oil into navigable waters or onto adjoining shorelines, and has more than 1,320 gallons of aboveground oil storage capacity (counting only containers of 55 gallons or more) or more than 42,000 gallons in completely buried tanks. If any one of those isn't true, the federal rule doesn't apply.
The federal SPCC rule (40 CFR Part 112) applies to a facility only when every part of the test in § 112.1(b) is met. EPA's own applicability questions follow the same order. Work through them one at a time; the first "no" ends it.
The test, in order
- Is the facility non-transportation-related? Factories, shops, farms, contractor yards, schools, hospitals, utilities, fuel distributors and most other fixed sites are. Oil in transit on the highway or rail (regulated by DOT) isn't. A site can be both, depending on what it's doing at the time.
- Do you drill, produce, gather, store, process, refine, transfer, distribute, use or consume oil? Storing diesel for your own equipment counts as storing and using. So does having transformers or hydraulic systems full of oil.
- Could a spill reasonably reach navigable waters or adjoining shorelines? This is judged on geography only: distance to streams, creeks, ditches and storm sewers that lead to them, land slope, drainage and soil. You must ignore dikes, berms, walls and other man-made structures that might stop the oil (§ 112.1(d)(1)(i)).
- Is your capacity over the threshold? More than 1,320 gallons of aggregate aboveground storage capacity, counting only containers of 55 gallons or more, or more than 42,000 gallons in completely buried tanks that aren't covered by the federal UST rules (§ 112.1(d)(2)).
Yes to all four means you need a written SPCC plan, and a new facility needs it in place before it starts operating (§ 112.3(a)(1)).
The step people get wrong: "could it reach water?"
Many owners assume they're exempt because there's no river next door. The rule's standard is broader. "Navigable waters" means waters of the United States as defined in 40 CFR 120.2, and oil can get there through a roadside ditch, a storm drain, a dry creek bed that runs after rain, or by soaking across a field. EPA's applicability guidance asks you to consider where oil would flow, how much could spill, soil conditions, and whether rain runoff could carry it. And the dike around your tank doesn't count in your favor at this step.
If you conclude a spill couldn't reach water, write down why, with the distances and drainage paths. If EPA disagrees later, that reasoning is what you'll be judged on.
Examples
| Facility | Aboveground capacity counted | Could reach water? | Plan needed? |
|---|---|---|---|
| Auto repair shop: 500-gal used oil tank, 275-gal new oil tote, four 55-gal drums of hydraulic fluid | 995 gal | Yes (storm drain at the curb) | No: under 1,320 |
| Same shop after adding a 500-gal waste antifreeze tank and a 550-gal diesel tank | 1,545 gal (antifreeze isn't oil, so the diesel is what tips it) | Yes | Yes |
| Equipment yard with a 2,000-gal diesel tank, 2 miles from any stream, flat ground, no ditches or storm sewers | 2,000 gal | Possibly not; document the analysis | Depends on the documented location analysis |
Illustrative. Ethylene glycol antifreeze is not oil; it doesn't count toward the threshold.
State rules can be stricter
The federal rule sets a floor. Some states regulate aboveground tanks with lower thresholds or their own plan requirements, and EPA notes that some states don't accept self-certified plans. Check with your state environmental agency even if you're under the federal numbers.
Related questions
Who is responsible for the SPCC plan?
The owner or operator of the facility. The rule puts the duty to prepare and implement the plan on the owner or operator (40 CFR 112.3), and a PE's certification doesn't shift that responsibility (112.3(d)(2)).
Can EPA require a plan even if I'm under the thresholds?
Yes. Under 40 CFR 112.1(f), the EPA Regional Administrator can require a facility to prepare a plan after written notice, even if it would otherwise be exempt. You get 30 days to respond before a final determination.
Find out where you stand, free
SpillPlan's free check tells you whether the SPCC rule applies, whether you can self-certify, how big your containment needs to be and what to inspect. If you need a Professional Engineer, it says so. The full plan kit is $549 if you want it.
Next questions
- How many gallons of oil require an SPCC plan?
- What isn't covered by the SPCC rule?
- What is considered oil under the SPCC rule?
- Tier I vs Tier II qualified facilities under the SPCC rule
Sources
- 40 CFR 112.1 — General applicability (1,320-gallon and 55-gallon thresholds, exemptions)
- 40 CFR 112.2 — Definitions (farm, oil-filled operational equipment, mobile refueler)
- 40 CFR 112.3 — Plan requirement, PE certification, qualified facility (Tier I / Tier II) criteria
- 40 CFR 110.3 — Discharges that "may be harmful" (the sheen rule)
- EPA — Does the SPCC rule apply to your facility?