How often does an SPCC plan need to be reviewed or updated?

Short answer

Review it at least every five years and sign a statement saying whether you'll amend it (40 CFR 112.5(b)). Separately, amend it whenever a change in design, construction, operation or maintenance materially affects the potential for a discharge: prepare the amendment within six months of the change and implement it within six months after that (112.5(a)).

An SPCC plan isn't a one-time document. Section 112.5 sets two separate clocks: a review every five years no matter what, and an amendment whenever the facility changes in a way that matters.

The two clocks

Five-year reviewAmendment for a change
TriggerFive years from when the facility became subject (or from the last required review)A change in design, construction, operation or maintenance that materially affects the potential for a discharge
DeadlineAt least once every five yearsPrepare within 6 months of the change; implement within 6 months after preparing it
What you produceA signed, dated statement that you reviewed the plan and will or won't amend it; amend within 6 months if a field-proven technology would significantly reduce discharge riskThe amended plan sections, certified
Rule§ 112.5(b)§ 112.5(a)

The review statement can go at the beginning or end of the plan, or in a log or appendix. The rule offers this wording: "I have completed review and evaluation of the SPCC Plan for (name of facility) on (date), and will (will not) amend the Plan as a result."

Changes that may require an amendment

Section 112.5(a) gives examples:

Administrative changes such as a new phone number or a new accountable person don't affect discharge potential, so they don't need a certified technical amendment; just update the plan.

Who certifies an amendment

Example timeline

A facility replaces two 500-gallon tanks with one 2,000-gallon tank on March 1. The amendment (new inventory, diagram, containment calculation and failure analysis) must be prepared by September 1 and implemented, meaning the new containment and procedures are in place, by the following March 1 at the latest. If the facility's five-year review is due that June, the review can be done alongside the amendment, but it still needs its own signed statement.

EPA-required amendments

EPA can also require changes. After a reportable discharge report or an on-site review, the Regional Administrator can require an amendment if the plan doesn't meet Part 112 or a change is needed to prevent discharges; you get 30 days to comment on a proposed amendment (§ 112.4(d)–(e)).

Related questions

Does replacing a tank require an amendment?

Usually. 40 CFR 112.5(a) lists commissioning, decommissioning, replacing, reconstructing or moving containers as examples of changes that may require an amendment. The test is whether the change materially affects the potential for a discharge; if it doesn't, an amendment isn't required, though keeping the container inventory current is still wise.

What wording does the five-year review need?

112.5(b) says this is enough: "I have completed review and evaluation of the SPCC Plan for (name of facility) on (date), and will (will not) amend the Plan as a result."